Have you noticed the bare, packed soil on Kalorama Park's slopes after a hard rain? Or water sheeting down the paths and stairs toward 19th Street? The city has. A $2 million erosion and stormwater project is scheduled to start at 1865 Kalorama Road NW this fall and finish in summer 2027. The D.C. Department of General Services manages it with the Department of Parks and Recreation, and the contractor is Atmos.
On the DGS project page, the status is "Permitting." The construction kick-off meeting with the community was held on Monday, November 9, 2026.
The project matters to anyone who uses the park daily, and the reason is simple. The problem is the hill itself, and the city has tried to fix that hill before. Its slope is also a National Underground Railroad Network to Freedom site, and the work will take place on that ground.
Where the water goes
The Kalorama Citizens Association describes Kalorama Park as "a three-acre wooded slope" at the highest point in the neighborhood. It sits on the north side of Columbia Road, between Kalorama Road and Mintwood Place. The western hillside looks out over the Rock Creek valley at sunset.
That height is what makes the view, and it also causes the erosion. Rain that falls at the top of a three-acre slope has to go somewhere. In Kalorama Park, it has been taking the soil with it.
The clearest account of why comes from a May 22, 2014 DGS community presentation. It blamed four things for the erosion:
- concentrated runoff
- compacted soils
- vegetation that never took hold
- heavy foot traffic
The same deck pointed to specific trouble spots. Too much runoff was flowing down the paths and stairs to 19th Street. Storm drains and stormwater features were underperforming, icing was a problem, and the 19th Street drainage system itself might have issues.
Anyone who has used those stairs on a wet January morning already knows the problem.
The second repair since 2014
The coming work follows an earlier one. DGS ran a Kalorama Park project from May 2014 to summer 2016. It covered anti-erosion and soil remediation, plaza and landscaping improvements, and playground work. The city's record lists $800,000 for the playground and $500,000 for plaza and landscaping improvements, both dated May 2016.
DGS describes the current project as dealing with site-work issues left from earlier projects, along with the runoff and erosion.
The budget shows how the priority has shifted. In the 2014 to 2016 project, the playground carried the largest of those two allocations. This time the entire $2 million goes to the ground: slopes, drainage, walkways and planting.
The project has been in public planning for nearly a year. DGS held community meetings on December 17, 2025, and March 26, 2026, before the November kick-off. Decks from all three meetings and a recording of the March session are posted on the project page.
What the plans show
The November 9 kick-off presentation groups the work under six headings:
- Natural erosion control
- Stormwater management
- Enhanced planting along the slopes
- Limiting compaction around heritage trees
- Replacing site furniture
- Repairing walkways and increasing accessibility
Two built features stand out in the deck. One is a retaining wall with slope planting. The other is a seat wall with understory planting where Kalorama Road meets Columbia Road. Anyone walking up Columbia Road passes that corner.
Trees take up much of the deck. It has a page on tree protection and treatment, separate lists of trees to be preserved, removed and planted, and a native planting palette.
Two of those headings line up with the 2014 diagnosis. Limiting compaction around heritage trees addresses the compacted soils that presentation named, and enhanced planting along the slopes addresses the vegetation that never took hold.
A hillside with a history beneath it
According to the Kalorama Citizens Association, the park's central grassy oval was the site of a 19th-century manor house, the operational center of John Little's large slave-holding farm. DGS's own meeting materials put that history up front. The March 26, 2026 deck has a page on park history and archaeology. It identifies the park as the former site of Little's home and the place connected to Hortense Prout's escape. It also notes that the National Park Service added Kalorama Park to the National Underground Railroad Network to Freedom in 2008.
The KCA notes that archaeological ruins of the farm still lie under the ground. Those ruins, together with the site's cultural history, led the city to nominate the park to the National Register of Historic Places in 2015. The park is also listed on D.C.'s African American Heritage Trail. In 2019, the Kalorama Citizens Association dedicated a historic marker in the park.
The park itself is something the neighborhood fought for. The KCA spent decades lobbying for it before it was dedicated in 1949. The association's parks page links to both the Underground Railroad nomination and the full National Register nomination for anyone who wants the complete account.
How the work will reach the park
The kick-off deck's logistics plan sends all construction vehicles in from 19th Street. It also shows a parking area for construction vehicles and a construction laydown area. The December 2025 deck marks the laydown area as fenced and puts construction vehicle parking on Kalorama Road.
If you walk a dog along Kalorama Road or cut through to 19th Street on the way to Columbia Road, those are the edges where the work will be most visible.
The schedule in the city's materials looks like this:
| Milestone | Date |
|---|---|
| Project kickoff and concept design meeting | December 17, 2025 |
| Revised design meeting | March 26, 2026 |
| Final design and construction kick-off meeting | November 9, 2026 |
| Construction start | Fall 2026 |
| Substantial completion | Summer 2027 |
The deck adds that timelines depend on factors such as permits and soil studies. Before you take children to the playgrounds or head to a plot in the community garden, check the DGS project page. It carries the current status, the posted presentations and a DGS contact for questions.
The park has a lot to keep in use around the work. The KCA counts two playgrounds, a basketball court, a community garden, a small shelter house and a plaza on the three acres, all around the oval and the western hillside.
If the schedule holds, substantial completion arrives in summer 2027, with the new slope plantings, repaired walkways and the seat wall at Kalorama and Columbia in place.
The NTB Group follows changes like this one because Kalorama's parks are part of the neighborhood's daily life. If you are a Kalorama owner wondering how the park's next year fits your own plans, The NTB Group would welcome a private conversation. You can find more on the neighborhood on our Kalorama page.